How much funding has Wellington City Council committed to finish the Karori Event Centre?

Wellington City Council has committed $1.9 million towards completing the Karori Event Centre. The Trust has worked with building professionals and contractors to review costs and identify how the project can be completed within this budget.

The Trust is responsible for fundraising for the remaining fit-out items, including retractable seating, furniture, technology and other essentials needed to make the centre ready for community use.

Why was the Karori Event Centre built?

The Karori Event Centre was developed to meet the growing need for a dedicated community space in Karori. Wellington City Council reports commissioned in 2006 and 2016 confirmed the need for a new community hall, a need that has continued to grow alongside the local population.

The centre will provide a welcoming, flexible venue for community groups, events, celebrations, meetings and activities, helping bring people together and supporting Karori’s growing community for generations to come.

How was the Karori Event Centre built and funded?

The Karori Event Centre was built by the Karori Community Hall Trust at a cost of approximately $2.8 million. More than $2 million was raised through community grants, donations and voluntary efforts, reflecting the community’s long-standing commitment to creating a dedicated space for local residents.

Wellington City Council also contributed $610,000 as an advance against the future sale proceeds of the St John’s site and a further $310,000 in costs avoided by not upgrading the former community halls on that site.

The project was made possible through a combination of community fundraising, local generosity and Council support.

What is the history of community halls in Karori and the timeline for this project?

The following is a short summary of the history of community facilities on the Karori site, of the gifts to WCC and the rationale for the development of the Karori Event Centre (KEC).

 1841 - The first community chapel was established on the land where the Karori Library now stands.

1893 - The Methodist Church purchased land on the corner of Karori Road and Campbell Street.

1923 - A church, school and parsonage had been established by this date, on adjoining properties.

 1959 - St John’s Church was built on the corner of Campbell St and Karori Road and the old church made available for community use.

 1987 - The parsonage had been converted into the Karori Lighthouse Community Centre as a joint venture between the Methodist Church and WCC. Several community facilities were now co-located on the corner of Karori Road and Campbell Street: the St John’s Church, the old wooden church hall, the old school building (used by the St John’s Op Shop) and the Lighthouse Community Centre.

1994 - The St John’s Church became a community hall.

1999 - The entire St John’s site was sold by the Methodist Church to WCC for $500,000, significantly less than the market value. The Methodist Church indicated at the time that the difference was a gift to WCC on the basis that the land would continue to be used for community purposes.

 2001 - Karori Town Centre Development Project was started by WCC. Key elements including a new community centre (on the current site of 7 Beauchamp Street) and moving the old wooden hall onto the current site of the KEC, for use as a community hall.

2005 - WCC decided that repurposing the wooden hall was too expensive. Later that year, the Replacement Community Hall Committee was formed which proposed the development of a new community hall to WCC. This recommendation was accepted by Council.

2007 - The Karori Community Hall Trust (KCHT) was established ‘to develop, design, build, equip and manage a multi-purpose community hall on land provided by the Wellington City Council adjacent to the Karori Community Centre in Karori, Wellington, as part of the community centre facilities’.

2007 - The old wooden hall and Lighthouse Centre were demolished.

2009 - Resource consent was granted for new community hall.

2011 - Fundraising for the KEC started.

2013 - WCC allocated $260,000 as a grant (equivalent to the cost avoided by not moving the old wooden hall + cpi). WCC also agreed to sell St John’s site and that the net proceeds would be allocated to KEC (consistent with the intent of the original gift of that site by the Methodist Church). These commitments were contingent on KCHT raising a further $1m.

2014 - The KCHT fundraising target of $1m was achieved.

 2016 - KCHT awarded a contract to construct the KEC having raised $2.8m. This included $610,000 from WCC as an advance on the net proceeds from the future sale of the St John’s site. KCHT did not have sufficient funds to complete the full build. However, because KCHT had $750,000 in grants for the build that would have expired, the decision was made to proceed and complete the base build to get a weather tight structure. The intention was to continue to raise funds for the fit out separately.

 2017 - The St John’s Church was demolished after being ‘yellow stickered’ as an earthquake risk.

Jan 2018 - Base build work of the KEC was completed on time and under budget.

2019 - KCHT made a submission to the WCC Annual Plan for 2019-20 to include $800,000 funding to complete the fit out. Fundraising efforts by KCHT had stalled due to changes in the fundraising environment post Kaikoura earthquake. This bid to WCC was declined, but councilors directed council officers to work with KCHT to resolve funding.

2020 - WCC approved a package of arrangements to complete the building and provide for future use of the facility by the community and Footnote New Zealand Dance Company. As part of those arrangements the Trust agreed to gift the completed building to WCC.

May 2022 – Footnote Dance NZ withdrew from the arrangement.

1 September 2022 – WCC agreed to $1.9 million capital funding to complete the KEC build and fit-out. They also agreed to accept the gift of KEC from the KCHT and noted that the capital project would be managed by WCC.

14 December 2022 - The Trust gifted the building to WCC prior to completion with the expectation that WCC would complete the required fit out for the long-awaited replacement community hall.

July 2023 – WCC officers again revised estimates for completion of KEC to about $3.2m. This included remedial works, deferred maintenance, and considerable added costs for increased fire protection and for costs arising from a flood impact assessment provided in February 2023. Those costs are associated with potential flooding caused by inadequate WCC storm water drains. The modeled flooding impacts lower Campbell Street and Karori Road, including the Karori Community Centre, Library, Mobil, and homes and premises in the surrounding areas. KCHT believes remediation costs should not be included in the KEC fit-out costs as they relate to a wider systemic problem that WCC needs to address separately. KCHT believe the KEC fit-out can be completed for the $1.9m still currently in WCC’s budget.

November 2023 - WCC  considers proposals to cut service levels for the Long Term Plan 2024-34. Included is a proposal to investigate selling the KEC which would also remove the $1.9m funding commitment from their budget. After lobbying from the Trust, Councillors removed the option of selling and asked for further information on the costs to complete KEC. WCC officers subsequently advised the Trust that they will be recommending the removal of the previously committed funding as part of the draft Long Term Plan. That decision will be made on 15 February 2024.

February 2024 – Following advocacy from the Trust, councillors removed the proposal to sell the Karori Event Centre from consideration and requested further information on the costs to complete it.

May 2025 – Wellington City Council agreed to offer the centre back to the Trust, with $1.9 million committed towards remediation and completion of the building.

2025–2026 – The Trust worked with building professionals and contractors to review the design, scope and costs. This included challenging some of Council’s estimates.

2026 – The Trust is progressing final designs, contractor quotes and arrangements for the building’s return to Trust ownership, alongside a supporting ground lease.

Next stage – The Trust is working towards construction, with completion timeframes to be announced once the remaining arrangements and construction programme are confirmed.